«FINANCE COMMITTEE MEETING held September 17, 2012 6:30 p.m. Present: Chairman Mike Young Councilman Dwight Clark Councilman Dave Tadych Also Present: ...»

-- [ Page 1 ] --

FINANCE COMMITTEE MEETING

held September 17, 2012

6:30 p.m.

Present: Chairman Mike Young

Councilman Dwight Clark

Councilman Dave Tadych

Also Present: Mayor Sutherland, Finance Director Presley, Service Director Galli

Audience: Councilwoman Lieske, Councilman Miller, Police Chief Wright, Fire

Chief Lyons, Operations Manager Landers

Mr. Young called the meeting to order at 6:30 p.m.

August Financial Statements Mr. Young stated that the financial statements of the city through the end of August have been received by the Finance Committee. Municipal Income Tax statements through August and the Health Care Fund Expenditures statement have also been distributed to Council. (Exhibits A, B, and C attached) Municipal Income Tax Mr. Young stated that municipal income tax receipts for the month of August have caused some consternation. Finance Director Presley informed Mr. Young that one of the reasons the receipts were low for the month was that a remittance normally received for the month was not received until the first week of September. Mr. Presley advised that the timing of the bills that should have gone out at the very beginning of August were delayed by ten days by the Regional Income Tax Agency. As a result, all of the receipts for August were delayed. Normally, in September, the city collects somewhere in the $300,000 range. In 2011, the city collected $330,000. Thus far, in September of this year we have collected over $583,000. There is still one more pay due from the city with an additional $4,500 in income tax. The Board of Education withholding for the month, which is generally in the low to mid-twenties, is still to be received. September collections will be slightly over $600,000, and year-to-date $3,915,000, down 3.92% compared to 2011. At the end of July, collections were down 5.35%.

Property Tax Mr. Young stated that the percentage of property tax collected as of the end of August is 94.08%.

Mr. Presley stated that there will be additional taxes collected this year, e.g., state homestead exemption, ten-percent rollback, and two-and-one-half percent rollback payments. These payments will come in late November or early December. Property tax for residential, commercial, and industrial property comes from the county, and by the end of the year Minutes of a Meeting of Finance Committee September 17, 2012 collections will total as close to 100% as possible. A delinquent property tax sale resulted in additional revenue, causing the increase from the average 97.5% collections.

Bayway Rental Income An estimate of $12,000 in revenue was posted and nothing has been received to date.

Sale of Recycling Materials The revenue received in the past when the city kept the recycling trucks at the garage will no longer be seen. The $15,000 posted as estimated revenue will be taken out when formulating the 2013 budget.

Miscellaneous Income Estimated revenue of $26,000 was posted, with year-to-date receipts of $1,208.60. Mr. Presley stated that he may have been considering that the energy efficiency grant would result in these proceeds. Mr. Tadych suggested looking back at the minutes of previous meetings to see what the thought was when putting this together.

Grant Revenue Revenue is over the estimate from this year and is from the SAFER Grant through the Fire Department. Reimbursement payments from last year, when the revenue was under estimate, have been received this year, causing the revenue to be over, but average out in total.

Court Fines Mr. Clark noted that the city has done well this year with court fines. He asked if there will have to be considered a possibility of reduction next year with the City of North Olmsted breaking away from the Rocky River Municipal Court. Mr. Presley stated that revenue will not be affected, but, depending on their expenses, a court subsidy may occur if the court expenses are not reduced to account for the loss of North Olmsted. Mayor Sutherland commented that the Rocky River Municipal Court has guaranteed that there is not going to be an additional cost to the participants. The Mayor stated further that she would not recommend the establishment of a Mayor’s Court for the City of Bay Village, noting that the Rocky River Municipal Court Judges have the expertise and resources to handle court cases.

Estate Tax Mr. Tadych noted that the year-to-date receipts of $678,238.69 are favorable for the city. He asked if the city is up-to-date on these collections. Mr. Presley stated that there is no way of knowing.

Property Tax Collections by Departments Minutes of a Meeting of Finance Committee September 17, 2012 Mr. Young noted that percentage of property tax collections year-to-date for the paramedic fund are shown as 87.35%, but Parks and Recreation is at 93.03%. Mr. Presley stated that he needs to review how those were budgeted versus what the county sent as estimated revenue, and see how those line up.

Cable TV Franchise Fee

Mr. Clark commented that the city does well with the cable television franchise fee revenue. The city establishes the percentage collected which is currently at 3%. The maximum allowable is 5%. Internet fees are not part of the fee basis; it is only for cable television and the amount is broken out by the provider.

Building Permits





Mr. Clark noted that building permit revenue has not been to the expected level, with only $57,657.99 collected year to date of the $105,000 estimated revenue. He questioned whether this may be connected to the spike that occurred in the last year or two. Mr. Young noted that electrical permits are above what was expected. This may indicate that improvements are being made, but not as much new construction.

Interest on Investments The revenue of $54,091.95 is exactly at 72.12% collections for the year’s estimate of $75,000.

Mr. Tadych stated that this is the first year that has occurred in many years.

Expenses versus Appropriations Mr. Presley distributed an analysis of variances, or exceptions, to the budgeted expenses for the year for review by the committee. As an example, Finance salaries are at a higher percentage for the year than they should be, for the reason that the salaries for the clerks that take the sewer payments have not been allocated to the sewer fund account. The Service Administration Wages line item does not reflect the Service Director who is allocated under Street Construction, Maintenance and Repair, and the Sewer Fund.

Mr. Tadych asked if the city is receiving any compensation from the gas lines that are being installed in the city from the use of our public lands. Mayor Sutherland stated that no compensation is being received other than income tax from the contractors. The Mayor stated that this has been discussed in the past. There are certain utilities, e.g., cable television, that are quasi-utilities, but the others could be very problematic. Some communities charge to work in the right-of-way resulting in a small amount of revenue, but affecting the working relationship with the utility companies.

Mr. Clark stated that the committee has discussed Bay Men’s Club Baseball and others paying more of their costs. He asked how the city has fared so far this year now that the season is over.

This will be discussed further when numbers are available.

Minutes of a Meeting of Finance Committee September 17, 2012 Supplemental Appropriation Ordinance 9-17-12 Mr. Presley reviewed the supplemental appropriation ordinance on this evening’s Council

meeting agenda as follows:

–  –  –

*Pursuant to agreement with Board of Education for the cost of capital improvement projects (City pays 2/3, Board of Education 1/3) Mr. Tadych asked if the city is doing just one mailing for the charter revisions. Mayor Sutherland stated that just one mailing will be done. The letter is being printed and will be mailed to each home at the end of September. Mr. Tadych noted that The Plain Dealer summarized the words the way they should be written on the ballot, making it understandable.

Mr. Tadych asked about the sidewalk repair resolution that is on the Council agenda for this evening’s meeting. Mr. Presley stated it is a block that was overlooked on the corner of Columbia and Wolf, and not included on the original list. Mr. Galli stated that they were not able to talk to the resident in this case about the settled sidewalk and decided to move ahead with the process. Mr. Tadych noted that a flashing light has been placed on the sidewalk by the Service Department. The sidewalk is level, but is cracked.

The resolution for the monthly fund transfer for the Council agenda this evening has the same fund transfer amounts that are done every month. The December transfers will change slightly due to rounding figures for the end of the year.

Mr. Tadych asked if any money will be received for the retiring leaf loader, with a new leaf vacuum loader being purchased through the passage of legislation this evening. Operations Manager Landers stated that the old vacuum loader will be kept for replacement parts.

Road Resurfacing Program Update Minutes of a Meeting of Finance Committee September 17, 2012 Mr. Young stated that Mr. Galli has furnished Council with a Summary of Completed Projects in Progress for the 2011-2012 period, dated September 14, 2012, and included spreadsheets with additional detail on these projects.

Mr. Young advised that going forward he would like to get a feel for cash flow, as far as major projects. For future meetings, a bond retirement schedule for proposed bonding will be helpful.

He asked Mr. Galli to provide the committee with his thoughts on future street reconstruction projects, including estimated dates and costs, for the years 2013 through 2015.

Mayor Sutherland stated that the administration will be working with Councilman Pohlkamp to review capital projects. The Mayor stated that they have always worked off of a revolving fiveyear plan, but when the city was hit with the findings and orders from the Environmental Protection Agency everything ground to a halt and they had to focus on whatever the EPA wanted the city to do. The three current projects lined up will take care of those issues. Road projects have been put on hold for the past three years because of the economy, and for the reason of focusing on the sewer projects. They are ready now to go back and piece together another five year capital projects plan. The Bay Park Beach Area is in terrible condition because of the construction they have had there. The roads in the Bruce/Russell area are bad and in need of attention.

Mr. Young stated that the facilities study listed the critical things that needed to be done for city buildings. Many of the items were roof related, so hopefully most of those dollars will come back from insurance proceeds. There was a balance of other items and it would be good to get an idea of the overall dollar figure of those items.

The Mayor stated that the administration will compile a list, and with guidance from the administration and Council they will prioritize where they need to go with those projects. Mr.

Gordon Evans of the Service Department has expressed concern for Lake Road on the west end.

The city might be able to partner with some other governmental entities but that will take time to explore and put together.

Mr. Young stated that a feel for the dollar figures and how those projects will be financed over the next three years will help with the budgeting process for next year.

Mr. Galli gave an overview of his 2011-2012 Public Improvement Project Update Summary, Exhibit D attached, stating that he has broken the projects down into three categories: Sewer Projects, Roads and Parks Projects, and Buildings.

Sewer Projects A pre-construction meeting has been held for the Cahoon Creek Aerial Sewer Replacement Project. The contractor will begin work when the material is delivered. Bridge traffic will be reduced somewhat during the project.

Minutes of a Meeting of Finance Committee September 17, 2012 The Cahoon Road Sanitary Sewer Replacement Project is in receipt of a $600,000 loan from the Ohio Public Works Commission. The project has been designed and a Public Improvements Committee meeting will be scheduled in early October with consulting engineer, CT Consultants in attendance to explain the project and review the information concerning design storms. The contract amount is not indicated in Mr. Galli’s summary.

The Lake Road Pump Station Project has not received any funding. The project is half-way through the analysis phase and the actual design phase will begin in the next month or two months. The Sanitary Sewer Interceptor Cleaning Project contract finals are considerably under budget.

Roadway and Parks Projects

The Bradley Naigle Road Improvements is anticipated to finish at $1,648,599.43. A $395,000 loan amount is projected, split with the City of Westlake. The rest of the funds will come from the grant. Mr. Young noted that 75 to 80% of the project is covered by the grant. Mr. Clark asked if all the bills are paid and if funds will be coming back to the Infrastructure Improvement Fund. Mr. Presley stated that an advance is out and Mr. Galli noted that about $340,000 will go out this week in payments. The city’s advance was $1.2 million. Mr. Galli noted that even though the city is paying an additional amount of $29,000 for the railroad crossing work, the total is still below the contract amount. At the end of the contract, a change order will be written for the contract deduction.

The Cahoon Park Tennis Court Project has mobilized and depending on weather conditions will be done as soon as possible.

The 2012 Pavement Maintenance and Resurfacing Project started last week on West Oviatt.

Repairs will take two to three weeks, asphalt work will be done, and the contractor will then move over to the Huntington Woods Project.

The Huntington Woods Project should begin in approximately two weeks. Milling and the first course of asphalt will be done as quickly as possible. Traffic will be maintained.



Pages:   || 2 |


Similar works:

«CURRICULUM VITAE Professor Christine Vivienne Helliar BSC, FCA, PhD, FRSA, FHEA, MISTC Recent positions From June 2012Head of School March 2016 School of Commerce University of South Australia Adelaide SA 5000 Australia Christine.helliar@unisa.edu.au To May 2012 Dean School of Business University of Dundee, DD1 4HN United Kingdom c.v.helliar@dundee.ac.uk January Chair 2010-date British Accounting and Finance Association United Kingdom www.bafa.ac.uk August 2003Director of Research (part time)...»

«chAPter 3 theoreticAl frAMeWork Human rights and labour violations perpetrated against trafficked persons have been documented in reports issued by numerous NGOs and intergovernmental organizations. The business implications of human trafficking, however, are less clear. In the previous chapter, the section on the Overlap between Upperand Underworld Activities provided limited insight into the impact that organized criminal activities can have on the legitimate economy. Unfair business...»

«Competition in the Dutch Flower Markets Ajit Kambil Eric van Heck Disclaimer: This case was prepared as a basis for class discussion rather than to illustrate either effective or ineffective handling of administrative and business situations. It frames the case in terms of a fictional meeting between the CIOs and the Board of the Dutch Flower Auctions for purposes of developing a decision problem and an educational case illustrating competitive strategy and the role of IT in auctions. This case...»

«Working Paper No. 179 THE EFFECTIVENESS OF THE LAW, FINANCIAL DEVELOPMENT, AND ECONOMIC GROWTH IN AN ECONOMY OF FINANCIAL DEPRESSION: EVIDENCE FROM CHINA by Susan Feng Lu Yang Yao* August 7, 2003 Stanford University John A. and Cynthia Fry Gunn Building 366 Galvez Street | Stanford, CA | 94305-6015 * Corresponding author. Corresponding address: China Center for Economic Research, Peking University, Beijing 100871, China. Email: yyao@ccer.pku.edu.cn. Yang Yao thanks Stanford Center for...»

«2012 International Journal of Economic Sciences Vol. I (No. 2) Major British Bank performance over the Business cycle Kalsoom Jaffar1* Robert Webb* Mabwe Kumbirai* Abstract: This paper investigates the effect of macroeconomic changes particularly the cyclical nature of bank performance using the dataset of Large British Banks over the period 2004-2011. Financial ratios are employed to investigate whether loan loss provision, lending rate, income level and return on asset show a cyclical...»

«PRIVATE ACTORS AND PUBLIC POLICY: A REQUIEM FOR THE NEW BASEL CAPITAL ACCORD by Michael R. King London School of Economics m.r.king@pobox.com & Timothy J. Sinclair University of Warwick timothy.sinclair@warwick.ac.uk © Michael R. King & Timothy J. Sinclair, 2003 PRIVATE ACTORS AND PUBLIC POLICY: A REQUIEM FOR THE NEW BASEL CAPITAL ACCORD Michael R. King London School of Economics and Timothy J. Sinclair University of Warwick ABSTRACT After the Asia crisis of 1997-98, policymakers invested much...»

«European Journal Accounting Auditing and Finance Research Vol.3, No.1, pp.20-29, January 2014 Published by European Centre for Research Training and Development UK (www.eajournals.org) FINANCIAL LITERACY EDUCATION: KEY TO POVERTY ALLEVIATION AND NATIONAL DEVELOPMENT IN NIGERIA Faboyede, Olusola Samuel PhD1, Ben-Caleb, Egbide2, Oyewo, Babajide3 and Faboyede, Adekemi4 1,2,3 Department of Accounting, School of Business, College of Development Studies, Canaanland, Ota, Ogun State, Nigeria. 4...»

«Alior Bank S.A. 1 Q 2014 Financial Results Announcement Conference Call held on 8 May 2014 Corporate Participants Wojciech Sobieraj Alior Bank S.A., CEO Witold Skrok Alior Bank S.A., Deputy CEO Michał Hucał Alior Bank S.A., Deputy CEO Katarzyna Sułkowska Alior Bank S.A., Deputy CEO Krzysztof Czuba Alior Bank S.A., Deputy CEO Niels Lundorff Alior Bank S.A., Executive Management Board Advisor Presentation Wojciech Sobieraj Alior Bank S.A. – CEO Good morning and welcome everyone to our...»

«Very Preliminary Comments Welcome Malaria and Early African Development: Evidence from the Sickle Cell Trait Emilio Depetris-Chauvin Brown University David N. Weil Brown University and NBER October 2011 Abstract We examine the effect of malaria on economic development in Africa over the very long run. Using data on the prevalence of the mutation that causes sickle cell disease we measure the impact of malaria on mortality in Africa prior to the period in which formal data were collected. Our...»

«PONDICHERRY UNIVERSITY (A Central University) DIRECTORATE OF DISTANCE EDUCATION Global Competitiveness and Retailing Paper Code: MBRM 4005 MBA RETAIL MANAGEMENT IV Semester Author Dr. Bushan D. Sudhakar Associate Professor Department of International Business School of Management Pondicherry University Puducherry All Rights Reserved For Private Circulation Only ISBN 978-93-81932-22-3 TABLE OF CONTENTS LESSON TITLE PAGE NO. UNIT 1.1 Global Competitiveness 3 I 1.2 Strategies, Models & Challenges...»

«North American Journal of Finance and Banking Research Vol. 1. No. 1. 2007. Seyed Mehdian, Mark Perry, & Rasoul Rezvanian THE EFFECT OF GLOBALIZATION ON EFFICIENCY CHANGE, TECHNOLOGICAL PROGRESS AND THE PRODUCTIVITY GROWTH OF U.S. SMALL AND LARGE BANKS Seyed M. Mehdian1. E-mail: seyed@umich.edu Mark J. Perry2. E-mail: mjperry@umich.edu Rasoul Rezvanian 3. E-mail: r-rezvanian@neiu.edu ABSTRACT A non-parametric approach is used to examine the effects of globalization and deregulation on the...»

«Department of Economics ECON 3405A Introduction to Public Economics: Taxation 2013 Winter Instructor: Professor Sohrab Abizadeh Office: B850 Loeb Phone: 613-520-2600 extension 3752 Email: s.abizadeh@uwinnipeg.ca OR sohrab_abizadeh@carleton.ca Office Hours: Wednesdays 12:30-2:15 pm or by appointment TA: TBA Office: TBA Office Hours: TBA Course Description and Scope: This course is intended to provide a general appreciation of the problems of government taxation policies. It will apply general...»





 
<<  HOME   |    CONTACTS
2017 www.thesis.dislib.info - Online materials, documents

Materials of this site are available for review, all rights belong to their respective owners.
If you do not agree with the fact that your material is placed on this site, please, email us, we will within 1-2 business days delete him.